QUESTION
NO: 1
___________
can change the priority of items in the _________ backlog at any time.
A.
The Product Owner(s); Sprint
B.
The Team; Product
C.
The Product Owner(s); Product
D.
The Scrum Master; Sprint
Answer:
C
QUESTION
NO: 2
During
the sprint review the project is assessed against the ___________
A.
Sprint goal
B.
Sprint Planning
C.
Sprint review
D.
Sprint retrospective
Answer:
A
QUESTION
NO: 3
How
many principles form the foundation of the Manifesto for Agile Software
Development?
A.
10
B.
9
C.
12
D.
15
Answer:
C
QUESTION
NO: 4
How
should the Product Backlog arranged?
A.
Product Backlog items should be sorted by level of effort or complexity in
descending order.
B.
Product Backlog items should be sorted by business priority in descending
order.
C.
Product Backlog items should be date sorted in ascending order.
D.
Product Backlog items should be grouped by business category or feature.
Answer:
B
QUESTION
NO: 5
How
should items in the Product Backlog be ordered?
A.
Prioritized across all business units and features first and then by list order
in the Product Backlog.
B.
Grouped by business features first and then chronologically by date of original
business
request.
C.
Alphabetically by the business unit first and then by list order in the Product
Backlog
D.
Chronologically by date of original business request first and then by list
order in the Product Backlog
Answer:
A